Works Contract


Contract No. CV/2022/03: Reconstruction of Leung Shuen Wan Pier, Sham Chung Pier and Sam Mun Tsai Village Pier




Contract Overview
The works include the reconstruction of the Leung Shuen Wan Pier with access ramp and reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform, and provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier.

Leung Shuen Wan Pier

Sham Chung Pier

Sam Mun Tsai Village Pier

Description

Contract No.
CV/2022/03
Scope
• Reconstruction of the Leung Shuen Wan Pier with access ramp;
• Reconstruction of Sham Chung Pier and Sam Mun Tsai Village Pier with floating platform;
• Provision of ancillary facilities such as roof cover, lighting system, benches, solar panels, Wi-Fi device at each pier;
• Provision of temporary berthing and mooring facilities during construction stage at each site; and
• Environmental mitigation, monitoring and audit for the works at each site.
Commencement Date
8 August 2022
Tentative Completion Date
2025
Contract Sum
HK$211.07M
Consultant
Mott MacDonald Hong Kong Limited
Contractor
Kat Yue Construction Engineering Limited

Leung Shuen Wan Pier

Aerial view of the existing Leung Shuen Wan Pier (Sep 2022)
General view of the existing Leung Shuen Wan Pier (Sep 2022)

Sham Chung Pier

Aerial view of the existing Sham Chung Pier (Sep 2022)
General view of the existing Sham Chung Pier (Sep 2022)

Sam Mun Tsai Village Pier

Aerial view of the existing Sam Mun Tsai Village Pier (Sep 2022)
General view of the existing Sam Mun Tsai Village Pier (Sep 2022)